Project management using point graphs
Mashood Ishaque, Abbas K. Zaidi, Alexander H. Levis · Systems Engineering · 2008
Abstract A graph‐based approach for scheduling and monitoring temporal events and activities in a system engineering project is presented. It attempts to overcome some of the limitations of traditional project management approaches by allowing specifications of real‐time milestones , and by breaking the finish‐start barrier between the activities. An example of a residential construction project is used to illustrate the approach. © 2008 Wiley Periodicals, Inc. Syst Eng