Risk analysis of construction diversion scheme
Yang Qingqing, Du Chengrong · E3S Web of Conferences · 2020
The determination of diversion risk in the construction of water conservancy and hydropower projects is a key problem related to the guarantee of project safety, saving project investment, giving full play to benefits in advance and facilitating construction. According to the design data, considering the influence of the uncertain factors such as hydrology and hydraulics, this paper analyses the relationship between the elevation of the upstream cofferdam and the upstream design water level, uses the Monte Carlo method to simulate the construction flood process and the discharge capacity of the diversion buildings, makes statistical analysis and determines the risk corresponding to the upstream water level distribution of the cofferdam and the water retaining height of the cofferdam, and establishes the calculation model of the construction diversion risk.