Calculus of the Resources Cumulative Task Using Different Technics and Software
Ilie Margareta · RePEc: Research Papers in Economics · 2017
The present paper main objective is to reveals how one can use two software application tools: Microsoft Project 2013 and Oracle Primavera P6 Professional for the project planning management, especially for industrial projects and for the calculus and graphical representation of resources cumulative task. The present planning consider four small processes with a total of 38 activities and seven resources. The two software are used for leveling the project’s resources and for giving the necessary information about the evolutions of cumulative tasks and how its values influences the cost of project. In conclusions comparison between the values and graphical representation presented by the two software shows differences of exemplifications, most of them from the graphical point of view.