AND/OR graphs and project management

Dušan Hvalica · Hrčak Portal of scientific journals of Croatia (University Computing Centre) · 1997

It is shown that projects can be described by AND/OR graphs and that the cost of the minimal solution subgraph can be defined so as to equal the shortest time for completing a project or the minimal costs of the project represented by the AND/ OR graph.