Study on Completion Probability with PERT for Hydropower Construction
Zhuo Wang · 2002
The limitation of the PERT in the planning of construction schedule is studied for two cases, where there are several critical paths, or the sub critical path is close to the critical path. The relativity and non relativity of the two cases are discussed respectively, and corresponding methods for calculation of completion probability are also proposed.