Integrated Research of Schedule Tracking Methods of Software Project
Liang Chengcai · Jisuanji gongcheng · 2007
Schedule is the top risk of software project,hence,it is a common focus on attention of customer and supplier.The schedule management mechanism of software project is described.The main six schedule tracking methods of software project used in the history such as milestone schedule,man-made activity schedule,working unit progress,earned value,gantt chart and network chart are compared and explained.Every method and its characteristics are described by explaining its calculation formulas,application time,application performance,evolution and other aspects.The best solution of schedule tracking of software project is recommended.