Application of Fuzzy Network Planning Technique in the Construction of the Water Conservancy Project
Wu Wenping, Ma Bin · Journal of Xi'an University of Technology · 2006
Based on the addition iteration formula for calculating fuzzy network time parameters and the hierarchical linear programming definition of fuzzy equation,this paper introduces the triangular fuzzy number into the analysis of construction duration to carry out an analysis of the construction network progress plan of the Shuhe hydropower station,whereby obtaining fuzzy time parameters,fuzzy critical path and fuzzy construction duration.The simulation results indicate that this method is so feasible and effective,that there is a great improvement in comparison with the traditional CPM and PERT models.