Deliverable 2 "Eight-month report - REACT project"

Christos G. Kaloudas, Luis F. Ochoa · 2014

This document presents the progress of the REACT project in terms of: a) data provision from DNOs and National Grid; and, b) production of OpenDSS network models of the selected critical and control GSPs, and identification of changes. In addition, the adequacy of the indices used in Deliverable 1 (based on yearly data) is verified by analysing half-hourly data. Finally, the load allocation technique used to estimate network points without data is illustrated with time-series simulations.

Read the paper · More papers on PaperTik