Fast-track production project cuts installation time in half

K. J. Vargas · Oil & gas journal/Oil and gas journal · 1991

This paper reports that fast tracking of a compressor and pipeline installation at Sylvan Lake, Alta., saved 6 months of project time. To succeed, fast tracking requires close coordination of all project activities, and ensuring that the shortest possible time be taken on critical activities. For example, by ordering critical equipment before formal approval and by finding a ready-built compressor, the Sylvan Lake project's duration was cut in half.